The New Build Project to date:
Case Study 1 - Sale Sports Club
Their project will be building a new clubhouse, all new astro & complete drainage project on all fields.
5-Year Sports Club Development Plan, and each section development plans all needed to be submitted to Sport England & all associated NGB’s ahead of any discussion regarding support for the project.
Spent 2 years to get to the point of planning approval. First stage was to bring together all member sections and generate buy-in. Members from each section are represented on project development committee. There are then a range of sub-committee’s setup through different stages of the project to address different aspects, all sub-committee’s have targeted skill-linked members to assist (Fundraising, Design, Interiors, etc).
Regular updates are provided to the entire SSC membership with open meetings held each quarter dedicated to the project.
SSC are also working closely with Trafford Council, particular focus on Playing Pitch Policies, reviewing facilities in the area and ensuring SSC are front & centre of Trafford’s initiative.
Financial support has been secured from Sport England, Trafford Council, LTA, RFU, FA, England Hockey, ECB (Grant & Loan) plus the sale of some land to housing developer.
Case Study 2